Weather risk for filming in Copenhagen

Three exterior days in Copenhagen in January: rain hits at least one with 80 % probability. In April it is 66 %. The tool is set to Copenhagen — enter your own days.

Three exterior days in Copenhagen: in January rain hits at least one of them with 80 % probability, in April with 66 %. Choose your month and number of days.
Climate data for 284 cities.

Plan by
100 %
100 % = any day with ≥ 1 mm rain is lost. Lower it if scenes can play in light rain or under cover.
Cover days for
At least one day hit
80 %
Expected lost days
—
Cover days to hold
—
Risk per day
—
Rain days in month
—
Sunshine per day
—
Daylight
—
Mean temperature
—

Your shoot, played out 20 times

Same number of days in every month — click a month

  • risk of at least one lost day
  • sunshine hours per day
Lost daysProbabilityThis many or fewer
Put cover days into a schedule

Runs in your browser. Nothing you enter is sent anywhere.

Rain risk in Copenhagen, month by month

Copenhagen averages 13 rain days in January and 9 in April. A rain day here is any day with at least 1 mm of precipitation, averaged over 2015–2024. The risk columns assume every exterior day can be lost; the cover-day column is what you need to be 90 % sure a five-day exterior block finishes.

Copenhagen: rain days and risk for 3 or 5 exterior days (Open-Meteo/ERA5, 2015–2024)
MonthRain days3 days: ≥ 1 hit5 days: ≥ 1 hitCover days (5 d, 90 %)Sun/dayMean temp
January1380 %93 %42.9 h2.4 °C
February1177 %92 %34.9 h2.7 °C
March1173 %89 %36.6 h4.0 °C
April966 %83 %310.4 h7.1 °C
May1069 %86 %312.2 h12.0 °C
June1070 %87 %312.8 h16.4 °C
July1380 %93 %412.1 h17.5 °C
August1277 %91 %311.0 h17.8 °C
September1175 %90 %38.9 h15.2 °C
October1380 %93 %45.3 h10.9 °C
November1278 %92 %33.2 h6.8 °C
December1380 %93 %42.2 h4.2 °C

When to shoot exteriors in Copenhagen

Weighing daylight against rain days, June comes out best: 17 h 30 min of daylight, 10 rain days and 12.8 hours of sunshine a day. The sunniest month is June (12.8 h a day).

The month matters here: five exterior days run a 83 % risk of losing at least one day in April, but 93 % in January — 3 against 4 cover days for 90 % certainty.

Rain days are not grey days: even in January, the wettest month, the sun shines 2.9 hours a day on average. Many of those rain days are wet for an hour, not all day — if your scenes can wait out a shower, lower the share slider in the tool.

Frequently asked

What is the rainiest month in Copenhagen?

January, with 13 days of at least 1 mm rain on average (2015–2024). The driest is April with 9.

How many cover days should I plan for an exterior shoot in Copenhagen?

For five exterior days and 90 % certainty: 3 in April, 4 in January. The tool above calculates it for your exact number of days.

Is this a weather forecast?