Weather risk planner

How many cover days does your exterior shoot need?

Pick a place, a month or your shoot dates and the number of exterior days. You get the chance of losing at least one, the days you should expect to lose, and how many cover days make the schedule safe.

Three exterior days in Hamburg: in July rain hits at least one of them with 86 % probability, in September with 70 %. Choose your month and number of days.
Climate data for 284 cities.

Plan by
100 %
100 % = any day with ≥ 1 mm rain is lost. Lower it if scenes can play in light rain or under cover.
Cover days for
At least one day hit
86 %
Expected lost days
—
Cover days to hold
—
Risk per day
—
Rain days in month
—
Sunshine per day
—
Daylight
—
Mean temperature
—

Your shoot, played out 20 times

Same number of days in every month — click a month

  • risk of at least one lost day
  • sunshine hours per day
Lost daysProbabilityThis many or fewer
Put cover days into a schedule

Runs in your browser. Nothing you enter is sent anywhere.

What the tool answers

Two questions decide an exterior block weeks before anyone looks at a forecast: which month to shoot in, and how many cover days to put in the budget. The tool answers both from ten years of daily weather data for the city — not with a percentage you have to interpret, but with the number of cover days that keeps the schedule standing in 80, 90 or 95 out of 100 versions of the shoot.

The grid plays your shoot out 20 times with the city’s rain frequency, so you can see what “70 %” looks like in practice: most versions lose one day, a few lose two, a few lose none. The strip below it shows the same number of days in every month, with sunshine hours as a dashed line — useful when the month is still open.

How we calculate

A rain day is a day with at least 1 mm of precipitation — less than that rarely stops a camera. For each city we count those days per month from daily ERA5 reanalysis data for 2015–2024 and average them over the ten years. Ten years instead of the meteorological thirty keeps recent summers in the picture.

Each exterior day is then treated as lost with probability p = rain days ÷ days in the month, multiplied by the share of rain days that would actually stop you. The number of lost days follows a binomial distribution (Poisson-binomial when your dates cross a month boundary). The cover days are the smallest number k for which “k or fewer days lost” reaches your chosen certainty.

p = rain days ÷ days in month × share that stops you P(≥ 1 day lost) = 1 − (1 − p)^n expected loss = n × p cover days k = smallest k with P(lost ≤ k) ≥ 80 / 90 / 95 %

Where the tool is wrong

  • Rain clusters. The model treats days as independent. Real rain comes in spells: the chance of losing at least one day is somewhat lower than shown, the chance of losing two or three in a row somewhat higher. If your block is long, hold the cover days together, not spread out.
  • 1 mm is not your threshold. A drizzle day counts the same as a downpour. Use the share slider: if half your scenes can play in light rain or under a roof, set it to 50 %.
  • Climate is not a forecast. These are averages of the last ten years. From about ten days before the shoot the national weather service is the better source; from three days the hourly forecast decides the call sheet.
  • One grid point per city. The data describes the city as a whole. Coast, mountains and valleys a few kilometres away can be markedly wetter or drier.

From the planning table

A three-day exterior shoot for a brand film in Hamburg, with the client asking for “summer”. July averages 15 rain days: three exterior days are hit at least once with 86 % probability, and 90 % certainty needs three cover days — as many as shooting days. September has 10 rain days: 70 % risk, two cover days. Same light for the brief, one cover day less in the budget.

Most of the scenes can play in light rain under the harbour roofs, so the producer sets the share slider to 50 %. September then comes to 42 % risk and one cover day. That one cover day — booked as a soft hold with crew and equipment — is the number that goes into the quote.

Weather risk by city

Rain days, risk tables and the best exterior month for 41 production locations. Every other city with climate data works in the tool above.

Frequently asked

What counts as a rain day?

A day with at least 1 mm of precipitation in the daily ERA5 data, averaged per month over 2015–2024. Days with a few drops below 1 mm do not count.

How many cover days should I book?

As many as the tool shows for the certainty you need. For most German cities and three to five exterior days that is two to four at 90 %. Short blocks in dry months often get by with one.

Why is the risk so high even in summer?

Because 1 mm is a low bar and summer showers are frequent in Central Europe. Many of those days are wet for an hour, not all day — that is what the share slider is for.

Can I use exact shoot dates instead of a month?

Yes. Switch to “Shoot dates”, enter the first exterior day and the number of consecutive days. If the block crosses into the next month, each day uses its own month’s rain frequency.

Why is my town missing?

Climate data is available for 284 cities. For a place in between, pick the nearest city with similar terrain — coast with coast, valley with valley.