Weather risk planner

Weather risk for filming in Madrid

Three exterior days in Madrid in March: rain hits at least one with 64 % probability. In July it is 9 %. The tool is set to Madrid — enter your own days.

Three exterior days in Madrid: in March rain hits at least one of them with 64 % probability, in July with 9 %. Choose your month and number of days.
Climate data for 284 cities.

Plan by
100 %
100 % = any day with ≥ 1 mm rain is lost. Lower it if scenes can play in light rain or under cover.
Cover days for
At least one day hit
64 %
Expected lost days
—
Cover days to hold
—
Risk per day
—
Rain days in month
—
Sunshine per day
—
Daylight
—
Mean temperature
—

Your shoot, played out 20 times

Same number of days in every month — click a month

  • risk of at least one lost day
  • sunshine hours per day
Lost daysProbabilityThis many or fewer
Put cover days into a schedule

Runs in your browser. Nothing you enter is sent anywhere.

Rain risk in Madrid, month by month

Madrid averages 9 rain days in March and 1 in July. A rain day here is any day with at least 1 mm of precipitation, averaged over 2015–2024. The risk columns assume every exterior day can be lost; the cover-day column is what you need to be 90 % sure a five-day exterior block finishes.

Madrid: rain days and risk for 3 or 5 exterior days (Open-Meteo/ERA5, 2015–2024)
MonthRain days3 days: ≥ 1 hit5 days: ≥ 1 hitCover days (5 d, 90 %)Sun/dayMean temp
January754 %72 %27.0 h5.1 °C
February544 %62 %28.4 h7.5 °C
March964 %82 %39.2 h10.1 °C
April966 %83 %310.8 h13.1 °C
May648 %66 %212.6 h18.0 °C
June542 %60 %213.3 h23.2 °C
July19 %15 %113.9 h27.7 °C
August218 %28 %112.7 h26.8 °C
September542 %60 %211.0 h20.8 °C
October964 %82 %38.6 h15.9 °C
November861 %79 %37.3 h9.7 °C
December754 %72 %26.4 h6.8 °C

When to shoot exteriors in Madrid

Weighing daylight against rain days, July comes out best: 14 h 47 min of daylight, 1 rain days and 13.9 hours of sunshine a day. The sunniest month is July (13.9 h a day).

The month matters here: five exterior days run a 15 % risk of losing at least one day in July, but 83 % in April — 1 against 3 cover days for 90 % certainty.

Rain days are not grey days: even in March, the wettest month, the sun shines 9.2 hours a day on average. Many of those rain days are wet for an hour, not all day — if your scenes can wait out a shower, lower the share slider in the tool.

Frequently asked

What is the rainiest month in Madrid?

March, with 9 days of at least 1 mm rain on average (2015–2024). The driest is July with 1.

How many cover days should I plan for an exterior shoot in Madrid?

For five exterior days and 90 % certainty: 1 in July, 3 in March. The tool above calculates it for your exact number of days.

Is this a weather forecast?

No — it is climate: what the last ten years looked like on average. From about ten days before the shoot, the national weather service forecast is the better source.