Weather risk planner

Weather risk for filming in Prague

Three exterior days in Prague in January: rain hits at least one with 77 % probability. In September it is 66 %. The tool is set to Prague — enter your own days.

Three exterior days in Prague: in January rain hits at least one of them with 77 % probability, in September with 66 %. Choose your month and number of days.
Climate data for 284 cities.

Plan by
100 %
100 % = any day with ≥ 1 mm rain is lost. Lower it if scenes can play in light rain or under cover.
Cover days for
At least one day hit
77 %
Expected lost days
—
Cover days to hold
—
Risk per day
—
Rain days in month
—
Sunshine per day
—
Daylight
—
Mean temperature
—

Your shoot, played out 20 times

Same number of days in every month — click a month

  • risk of at least one lost day
  • sunshine hours per day
Lost daysProbabilityThis many or fewer
Put cover days into a schedule

Runs in your browser. Nothing you enter is sent anywhere.

Rain risk in Prague, month by month

Prague averages 12 rain days in January and 9 in September. A rain day here is any day with at least 1 mm of precipitation, averaged over 2015–2024. The risk columns assume every exterior day can be lost; the cover-day column is what you need to be 90 % sure a five-day exterior block finishes.

Prague: rain days and risk for 3 or 5 exterior days (Open-Meteo/ERA5, 2015–2024)
MonthRain days3 days: ≥ 1 hit5 days: ≥ 1 hitCover days (5 d, 90 %)Sun/dayMean temp
January1277 %91 %34.0 h0.9 °C
February1073 %89 %35.8 h2.6 °C
March1069 %86 %37.7 h5.3 °C
April1070 %87 %39.6 h9.6 °C
May1277 %91 %310.7 h14.4 °C
June1278 %92 %312.3 h19.6 °C
July1173 %89 %312.4 h21.0 °C
August1173 %89 %310.8 h20.8 °C
September966 %83 %39.1 h16.0 °C
October1173 %89 %36.4 h10.9 °C
November1070 %87 %34.3 h5.2 °C
December1173 %89 %33.9 h2.6 °C

When to shoot exteriors in Prague

Weighing daylight against rain days, July comes out best: 15 h 58 min of daylight, 11 rain days and 12.4 hours of sunshine a day. The sunniest month is July (12.4 h a day).

The rain risk barely moves through the year in Prague: five exterior days run a 83 % to 92 % risk of losing at least one day, whatever the month. Choosing the month buys you little here; cover days and a flexible schedule buy you more.

Rain days are not grey days: even in January, the wettest month, the sun shines 4.0 hours a day on average. Many of those rain days are wet for an hour, not all day — if your scenes can wait out a shower, lower the share slider in the tool.

Frequently asked

What is the rainiest month in Prague?

January, with 12 days of at least 1 mm rain on average (2015–2024). The driest is September with 9.

How many cover days should I plan for an exterior shoot in Prague?

For five exterior days and 90 % certainty: 3 in September, 3 in January. The tool above calculates it for your exact number of days.

Is this a weather forecast?

No — it is climate: what the last ten years looked like on average. From about ten days before the shoot, the national weather service forecast is the better source.